Text-only Description for Workday ERP (Enterprise Resource Planning) Project Timeline

Presentation

An infographic with a horizontal timeline that is organized by month from February 2022 to February 2023 with a forward arrow.

Information

February - April 2022

  • Plan
    • Project
      • Host discovery sessions, identify requirements and current practices
    • OC&T (Collaborative Solutions' Organisational Change & Training)
      • Understand organization, set key milestones and dates for deliverables

May - June 2022

  • Alignment
    • Project
      • Gather requirements for MSU Workday design
    • OC&T
      • Capturing change impacts, identifying stakeholders

July - August 2022

  • Configure & Prototype
    • Project
      • Validating MSU Denver’s Workday design
    • OC&T
      • Finalize Change Impacts, Roll out Communications

September - November 2022

  • Test & Parallel
    • Project
      • Ensure Workday system is configured as designed
    • OC&T
      • Training Development
      • Training – Late Fall

December 2022

  • Plan
    • Deploy
      • Workday updates coming from E2E (end-to-end) testing
    • OC&T
      • Training Delivery

January 2023

  • Go Live!

January - February 2023 (with forward arrow)

  • Post-Production
    • Project
      • Post-Production Support
    • OC&T
      • Sustainment Strategy deployment

Your workday: Reimagined, Transformed, Simplified

MSU Denver logo on lower-left side of image and Workday logo on lower-right side of timeline image


Return to the Workday Project Background webpage - Project Timeline section